September 22, 2023

MAIN STREET MULTIMODAL PROJECT

(ALMOND ST TO OAKDALE AVE)

Downtown Medford Main Street Striping

ROADWAY STRIPING INSTALLATION UPDATE

PROJECT SCHEDULE:
Expected start date: September 26th, 6pm or later.

Work schedule: Sunday nights through Friday mornings, between 6pm and 7am.
(If work shifts to daytime, hours would be 8:30am-4pm, Monday-Friday)

Expected duration: 2-3 weeks.

Contracted completion date: October 27th.
Thank you for your patience and flexibility during this time.

Note: This schedule is subject to change on short notice as the work is heavily weather and
temperature dependent. Exceptions to the plan described above may be made due to extenuating
circumstances.

WHAT TO EXPECT:
Temporary traffic control measures will be in place while workers are on-site. Temporary traffic
control measures may be left in place while the Contractor is not working, depending on the
roadway conditions.


Daily, during daytime hours, at least two travel lanes on Main Street will remain open and
at least one side of each block will be available for parking. Cross streets may have parking
restrictions near the intersections with Main Street, as needed for the Contractor to complete
the work in the intersections. No parking signs will be posted where restrictions are in place.

For project website and plans. Visit website

Contact Information
For Questions or Comments
Christina Charvat
Traffic Engineering, Public Works Department
541-774-2118, Email